You are here: Use Enterprise Timetabler > Edit resource allocation > List pending resource requests

List pending resource requests

When you schedule or reschedule an activity, or edit its resource allocation, Enterprise Timetabler might generate resource requests. Enterprise Timetabler can list activities that are associated with resource requests that your actions generated, but have not yet been granted or denied.

To list pending resource requests, follow this step:

  • Click Pending Requests (out) in the Status pane.

    Tip: To see which resources are pending approval, click an activity in the Activity pane, then click the Resources tab. If a resource name is suffixed with '(Requested)', its allocation is pending approval.